Location
131km from the east coast of Yorkshire
Wind turbines
GE Haliade-X, 12MW
Number of turbines
95
Total capacity
1,2 GW
Owner & developer
SSE/Equinor
Client Sif
SSE/Equinor
Foundation
Monopiles and transition pieces
Water depth
18-63 meter
Weight monopiles
103.087
Diameter monopiles
8-8,6 meter
Length monopiles
54,9-71 meter
Weight transition pieces
35.941
Diameter transition pieces
8-8,3 meter
Length transition pieces
27 meter
Dogger Bank A
Dogger Bank Wind Farm is an offshore wind farm being developed in three phases – Dogger Bank A, B and C – located between 130km and 190km from the North East coast of England at their nearest points.
Collectively they will become the world’s largest offshore wind farm.
Each phase will have an installed generation capacity of 1.2GW. Combined, they will have an installed capacity of 3.6GW and will be capable of powering up to 6 million homes.